  • Startdate:

    2019/05

  • Enddate:

    2026

  • 2026: Assembly of storage ring planned.
  • 2023: Technical design report (TDR) of the storage ring started - Link.
  • 2023/10: Electron beam after upgrade of injector and modulator.
  • 2023: Photographs of the new RF photoinjector (left) and 10 MW RF unit (right) installed at FLUTE.
  • FLUTE photoinjector and 10 MW RF modulator
  • 2021/01: Ordering modulator incl. klystron for linear accelerator system.
  • 2020/10: Ordering modulator incl. klystron for photo-injector system.